Dam & Safety ›› 2020, Vol. 0 ›› Issue (1): 12-.
Previous Articles Next Articles
WANG Dongliang, WANG Hongtao and ZHU Anlong
Received:
Revised:
Online:
Published:
王栋良,王红涛,朱安龙
作者简介:
Abstract: The Kengwei gully where the upper reservoir of Zhouning pumped storage power station is located is a small thin debris flow gully. And Zhouning power station, Long'er power station camp, access tunnel of Zhouning power station, and access tunnel of Zhouning pumped storage power station, construction camp and other buildings are distributed downstream the Kengwei gully which are at risk of debris flow. Therefore, control measures are put forward to reduce potential risk of debris flow, for reference.
Key words: Zhouning pumped storage power station, Kengwei gully, debris flow, buildings, control
摘要: 周宁抽水蓄能电站上水库所在的坑尾沟为小型稀性泥石流沟,坑尾沟下游分布有周宁电站及龙二电站营地、周宁电站进厂交通洞,以及周宁抽水蓄能电站进厂交通洞、施工营地等建筑物,泥石流爆发安全威胁大,因此,笔者对坑尾沟泥石流治理设计进行了介绍,以降低泥石流爆发的威胁。
关键词: 周宁抽水蓄能电站, 坑尾沟, 泥石流, 建筑物, 治理
WANG Dongliang, WANG Hongtao and ZHU Anlong. Control measures for debris flow in Kengwei gully of Zhouning pumped storage power station[J]. Dam & Safety, 2020, 0(1): 12-.
王栋良,王红涛,朱安龙. 周宁抽水蓄能电站坑尾沟泥石流防治方案研究[J]. 大坝与安全, 2020, 0(1): 12-.