Abstract: Seepage monitoring of asphalt concrete faced rockfill dam and the inlet/outlet of upper reservoir is carried out. And the monitoring data is analyzed. Combined with dam operation and other monitoring data, the seepage of upper reservoir is evaluated.
Key words: Zhanghewan pumped storage power station, upper reservoir, seepage monitoring
摘要: 主要对张河湾抽水蓄能电站上水库沥青混凝土面板堆石坝和上水库进出水口的渗流观测资料进行分析,并结合上水库大坝的运行工况及其他相关观测资料分析整个上水库的渗流情况。
关键词: 张河湾抽水蓄能电站, 上水库, 渗流观测