LI Ji-gong and WU Feng-ji
Online:
Published:
李继功,吴凤吉
Abstract: This paper introduced the tailrace dredging at Hongshi hydropower station and analysed its profit.
摘要: 红石水电站尾水清挖完成后,平均尾水位降低了0.49 m,平均每年增加发电量753 万kW·h,取得了发电效益,本文对此作一简要介绍。
李继功,吴凤吉. 红石水电站发电尾水河床清挖工程效益分析[J]. .