• Operation management • Previous Articles     Next Articles

Analysis on tailrace sedimentation after flood discharge and power loss at Taipingwan hydropower station

LIANG Zhihai, YUAN Lian-qing, ZHANG Qing-fu and et al.   

  • Online:2009-08-28 Published:2009-08-28

太平湾电站泄洪后尾水渠淤积与电能损失的分析

梁志海,袁连庆,张庆福,魏樱   

  1. 东北电网有限公司太平湾发电厂,辽宁丹东 118000

Abstract: Taipingwan hydropower station is of daily regulation, low head and large flow, thus tailrace sedimentation may cause power loss. This paper discussed this issue, for reference.

摘要: 太平湾电站为日调节、低水头、大流量水电站,尾水渠淤积后,因水头减小而造成电能损失,本文对此问题进行简要分析,供探讨。