Dam & Safety ›› 2022, Vol. 0 ›› Issue (6): 48-.
Previous Articles Next Articles
XU Lei, YANG Ge and LIU Hui#br#
Received:
Revised:
Online:
Published:
许 雷1,2,杨 鸽1,刘 慧1
作者简介:
基金资助:
Abstract: According to GB 18306—2015 Seismic Parameter Zoning Map of China, the ground motion peak acceleration of a pumped storage power station is adjusted from 0.138g to 0.2g and seismic basic intensity is adjusted from 8 to 9. To evaluate the seismic safety of the dam, the dynamic time-history method and the quasi-static method are used for the review calculation of typical sections. The calculation results show that the vertical residual deformation of the dam after the earthquake is less than 0.6% of the maximum dam height. There are three small-scale sliding bodies at the top of the dam, which exert no harmful effect on the overall safety. The slope stability of different sections are all greater than the requirements in the specification. The calculated elevation of the wave barrier crest is lower than the minimum elevation of the measured wave barrier crest under the condition of 9-degree earthquake. Therefore the seismic safety of the dam can satisfy the requirements from the current specification.
Key words: seismic safety, face slab rockfill dam, dam slope stability, dynamic time-history method,  , quasi-static method
摘要: 根据新版GB 18306—2015《中国地震动参数区划图》,某抽水蓄能电站下水库主坝基岩水平地震动峰值加速度由0.138g调整至0.20g,相应地震烈度由Ⅷ度升至Ⅸ度。为了评价大坝抗震安全性,选择典型断面采用动力时程法和拟静力法进行复核计算,计算结果表明,坝体震后竖向残余变形小于坝高的0.6%,坝顶处存在三个规模很小的滑动体,但不影响坝体整体安全稳定性,不同断面下游坝坡抗滑稳定安全系数均大于规范要求,Ⅸ度地震工况下防浪墙顶计算高程低于实测防浪墙顶最低高程,大坝抗震安全性满足现行规范要求。
关键词: 抗震安全性, 面板堆石坝, 坝坡稳定, 动力时程法, 拟静力法
CLC Number:
TV698.1
XU Lei, YANG Ge and LIU Hui. Seismic safety review of lower reservoir dam of a pumped storage power station[J]. Dam & Safety, 2022, 0(6): 48-.
许 雷, 杨 鸽, 刘 慧. 某抽水蓄能电站下水库主坝抗震安全性复核分析[J]. 大坝与安全, 2022, 0(6): 48-.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://magtech.dam.com.cn/EN/
http://magtech.dam.com.cn/EN/Y2022/V0/I6/48
[2] 国家能源局.NB 35047—2015,水电工程水工建筑物抗震设计规范[S].北京:中国电力出版社,2015.
[3] 朱晟,杨鸽,周建平,等“. 5·12”汶川地震紫坪铺面板堆石坝静动力初步反演研究[J].四川大学学报(工程科学版),2010,42(5):113-119. [4] 郑惠峰,周廷清,孙来,等.苗尾水电站砾质土心墙堆石坝抗震复核分析[J].大坝与安全,2021(2):1-5. [5] 翟洁,张毅,李萌,等.十三陵抽水蓄能电站上水库面板堆石坝抗震复核分析[J].大坝与安全,2018(3):7-12. [6] NB/T 10872-2021,碾压式土石坝设计规范[S].北京:中国水利水电出版社,2022.