Design of deformation monitoring and its monitoring data of Yunfeng dam

YU Jian-jun, JIANG Dian-wei and XUE Han-jun   

  • Online:2009-08-28 Published:2009-08-28

云峰水电站大坝变形监测设计及监测成果

于建军,姜殿威,薛捍军   

  1. 东北电网有限公司云峰发电厂,吉林集安 134200

Abstract: Yunfeng dam is a slotted gravity dam. To monitoring its deformation, vacuum laser collimation system, wire alignment, vertical lines and hydrostatic leveling system were adopted and dam deformation monitoring was realized. This paper introduced its design process, for reference.

摘要: 云峰水电站大坝为混凝土宽缝重力坝,为掌握大坝变形,研究坝体的变形规律,综合运用真空激光准直系统、引张线、垂线及静力水准系统等几种变形监测方法,成功实现了对大坝的变形监测,为大坝变形监测设计提供了宝贵的经验。