Research and design of monitoring system for total seepage in dam foundation of Daheiting reservoir

ZHAO Lifeng   

  1. Management Bureau of Luan River Diversion Project, Haihe River Water Conservancy Commission, MWR
  • Received:2021-11-22 Revised:2021-12-23 Online:2023-02-10 Published:2023-04-18

大黑汀水库大坝坝基总渗流量监测系统的研究和设计

赵利锋   

  1. 水利部海河水利委员会引滦工程管理局,河北 唐山,064300
  • 作者简介:赵利锋(1981—),男,河北唐山人,高级工程师,主要从事大坝安全监测工作。

Abstract:

Daheiting reservoir has been in operation for more than 40 years. The total seepage in main dam foundation is obtained from the sum of regional seepage in dam gallery. Because the dam seepage is relatively scattered, the total seepage can't be obtained by regional monitoring points. Therefore, the existing monitoring data can not exactly reflect the total seepage, which affects the analysis of seepage data. To solve this problem, the total seepage in dam foundation can be obtained by monitoring the water level change in water collecting wells and the amount of water forcibly discharged from water collecting wells to downstream, which meets the monitoring requirements and improves the project management level.

Key words: safety monitoring, total seepage, monitoring system

摘要:

大黑汀水库已建成运行40多年,主坝坝基总渗流量由坝体廊道内分区渗流量求和得到。由于坝体内渗流 较分散,分区监测点未能监测到全部渗流量,因此现有监测数据不能完全反映坝基总渗流量,影响渗流量监测数 据分析。为解决该问题,监测了坝体内集水井水位变化和集水井强制排向下游水量,求得了坝基总渗流量,满足 监测要求,提高了工程管理水平。

关键词: 安全监测, 总渗流量, 监测系统