Dam & Safety ›› 2021, Vol. 0 ›› Issue (3): 39-.

Previous Articles     Next Articles

Optimization and study on large-diameter three-girders reinforced branch pipe at the bottom of surge chamber of a pumped storage power station#br#

YAO Minjie, WANG Jianguo, LI Gaohui and WANG Songxiang#br#   

  1. PowerChina Huadong Engineering Co., Ltd.
  • Received:2021-03-31 Online:2021-06-08 Published:2021-11-25

某抽水蓄能电站引水调压室底部大直径三梁钢岔管优化研究

姚敏杰,汪剑国,李高会,王颂翔   

  1. 中国电建集团华东勘测设计研究院有限公司,浙江  杭州,311122
  • 作者简介:姚敏杰(1983— ),男,浙江杭州人,本科,高级工程师,研究方向为水工结构。

Abstract: Steel lining is adopted for the water conveyance system of a pumped storage power station, and a restricted orifice surge chamber is set at the end of headrace tunnel. A three-girders reinforced branch pipe is set to connect the main pipe and surge chamber which a large diameter and complicated stress condition. Three-dimensional finite element method is used to optimize and study this three-girders reinforced branch pipe, to propose a reasonable and feasible shape.

Key words: three-girders reinforced branch pipe, three-dimensional finite element method, optimization and study, Mises stress

摘要: 某抽水蓄能电站输水系统采用全钢衬布置,在上平洞末端设置阻抗式调压室,调压室底部设置三梁钢岔管连接上平洞主管与阻抗孔支管。岔管主管直径大、结构受力复杂。运用三维有限元法对管结构进行了优化研究,推荐了合理可行的三梁钢岔管体型。

关键词: 三梁岔管, 三维有限元, 优化研究, Mises应力

CLC Number: