Flood forecasting and warning mechanism during construction of a hydropower station

ZHONG Weibin, REN Jinming, PU Ning and ZHENG Nan   

  1. PowerChina Huadong Engineering Co., Ltd.
  • Received:2019-09-23 Online:2019-12-20 Published:2019-12-08

某水电站施工期洪水预报预警机制

钟伟斌,任金明,蒲  宁,郑  南   

  1. 中国电建集团华东勘测设计研究院有限公司,浙江  杭州,311122
  • 作者简介:钟伟斌(1981— ),男,浙江长兴人,高级工程师,主要从事水利水电工程施工组织设计工作。

Abstract: As floods rise up and down sharply in Yarlung Zangbo River during the flood season, a hydropower station adopts three-level forecast system (short-term, medium-term and long-term) and four-level warning mechanism (blue, yellow, orange and red), which successfully helped the resistance of the 2018·08 catastrophic flood. It can serve as a reference for similar projects.

Key words: Yarlung Zangbo River, flood during construction, forecasting and warning mechanism, emergency response

摘要: 针对雅鲁藏布江汛期洪水暴涨暴落的特点,某水电站工程采用短期、中期和长期三级预报系统,蓝、黄、橙、红四级预警机制,成功抵御了“2018·08"特大洪水,相关预警方案和响应机制可供类似工程借鉴参考。

关键词: 雅鲁藏布江, 施工期洪水, 预报预警机制, 应急响应