Design study on construction scheme of water level regulation project for Shuikou downstream hydro-junction

HU Xiao-wen, JIANG Jin-zhang, YU Qing and et al.   

  • Online:2011-10-28 Published:2011-10-28

水口坝下水位治理工程建设方案设计研究

扈晓雯,江金章,于青,芮德繁   

  1. 中国水电顾问集团华东勘测设计研究院,浙江杭州 310014

Abstract: The main objective of water level regulation project for Shuikou downstream hydro-junction was to solve the problem of inadequacy of threshold depth of navigation structure and meet the requirements on the draft head of hydro-generator. By construction of downstream junction, the water level would reach 7.64 m while discharge is 308 m3/s. During operation of Shuikou hydropower plant, its available water head is limited. The comprehensive analysis showed that the navigation scheme was preferred to navigation and hydropower scheme.

摘要: 水口水电站枢纽坝下水位治理工程的目的是解决通航建筑物门槛水深不足和水轮发电机组的吸出高度达不到设计要求的问题,通过修建下游枢纽使水口水电站坝下水位在泄放流量为308 m3/s时达到7.64 m。工程位于闽江下游,多年平均流量达到1 680 m3/s,水口水电站正常运行时,坝下枢纽能利用的水头有限。下游枢纽究竟采用航运方案还是航电方案,通过经济技术综合比较,确定工程建设任务。