Design of construction diversion scheme of water level regulation project for Shuikou downstream hydro-junction

WU Bin and JIANG Jin-zhang   

  • Online:2011-10-28 Published:2011-10-28

水口坝下水位治理工程施工导流规划设计

吴彬,江金章   

  1. 中国水电顾问集团华东勘测设计研究院,浙江杭州 310014

Abstract: According to the hydrology, geology and construction diversion condition, the paper introduced the design for construction diversion, for reference.

摘要: 结合水口水电站坝下水位治理工程的水文、地形地质、施工导流等特点,确定了施工导流设计方案,供类似工程参考。