Abstract: After the completion of Gandjelas dam construction, seepage of abutment above 1 529.80 m occurred when the water level was 1 545.0 m.Aiming at the seepage, curtain grouting on the dam abutment was carried out. The qualified rate in water pressure test was 100% and the collecting rate of drill core was high, which showed the grouting was of good effect.
摘要: Gandjelas 大坝建成后,当蓄水到1 545.00 m 高程时,坝肩1 529.80 m 高程以上部位出现渗漏。针对渗漏情况,在坝肩适当范围内进行帷幕灌浆处理,灌浆后压水试验合格率100%,岩芯采取率高,满足设计要求。
姜卫超,邓莹莹. 帷幕灌浆技术在Gandjelas 大坝坝肩渗漏处理中的应用[J]. .