Previous Articles     Next Articles

Dam filling and its quality control inYinzidu hydropower station

CHENG Kai and ZHU Xiao-sheng   

  • Online:2004-04-28 Published:2004-04-28

引子渡水电站面板堆石坝填筑与质量控制

程凯,朱孝生   

  1. 中国水利水电第十二工程局六分局,浙江金华 321027

Abstract: It costs15months overall from initial dam filling to impounding in Yinzidu project, the most filling intensity every month is up to 403 thousand m 3. Under those restricted requirement of complicated construction condition, strict quality control and limiting con-struction time, the contractor have made an effort to create harmony of quality and progress.?

摘要: 引子渡水电站拦河坝,从开始填筑到下闸蓄水总历时15个月,最高月填筑强度达40.3万m3。在复杂的施工条件严格的质量控制和紧张的工期要求下,创造了质量与进度的双赢。