• 变形监测 • 上一篇 下一篇
程渭炎,陈绪春,郭祚界
发布日期:
CHENG Wei-yan CHEN Xu-chun and GUO Zuo-jie
Published:
摘要: 本文就三峡工程双线五级船闸的各闸首、闸墙在施工、调试、试运行过程中受充泄水、外界气温变化、闸门开闭等因素影响的变形情况做了初步分析。建筑物变形总体不大,无异常现象。
Abstract: The paper has preliminarily analyzed the deformation of all lock heads and lock walls in double-line five-grade ship lock at Three Gorges Project. In the course of construction, test and initial operation process, which is effected by the filling & leasing water, the outside temperature variety and opening & closing the lock, etc. The total deformation of the structure is not obvious, and there isn’t any abnormal phenomenon.?
程渭炎,陈绪春,郭祚界. 三峡工程双线五级船闸边墙变形初步分析[J]. .
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://magtech.dam.com.cn/CN/
http://magtech.dam.com.cn/CN/Y2004/V0/I4/11