• 贵州引子渡水电站工程建设专辑 • 上一篇    下一篇

引子渡水电站厂房设计

李字,陈敬   

  1. 国家电力公司贵阳勘测设计研究院,贵州贵阳 550002
  • 出版日期:2004-04-28 发布日期:2004-04-28

Onpowerhouse designing of Yinzidu hydropower station

LIYu and CHEN Jing   

  • Online:2004-04-28 Published:2004-04-28

摘要: 引子渡水电站为引水式地面厂房,厂区布置紧凄,无施工干扰。由于施工工期紧,设计上采用轻型屋面网架结构、钢结构吊车粱等优化设计,施工采用滑模施工技术代替传统混凝土浇筑方法,对缩短工期起到了有效作用,解决了目前在建工程工期短的一些问题。

Abstract: Yinzidu hydropower station has diversion-type ground powerhouse with the characteristics of compact layout and not disturbed by construction.Light roof netting frame structure is designed to be used,optimizing the design of steel structure crane beam and sliding frame technology are adopted in construction instead traditional concrete placement.Those measures have much effect on cutting construction time.?