Abstract: In order to monitor project’s safety status of every section,it is designed to arrange some interrelated instruments at slope,dam,spillway and diversion tunnel.Observational instruments embedded in high quality and data collected timely will give a bene-ficial direction for other projects.?

摘要: 为了监测各工程部位安全状态,设计分别在边坡、大坝、溢洪道、导流洞等工程部位布置了相关观测仪器。观测仪器高质量的埋设和资料的及时收集整理给工程施工提供了有益指导。