• Data analysis • Previous Articles Next Articles
XU Jun - jie
Online:
Published:
徐俊杰
Abstract: After lowpressure thick curtain grouting treatment to Shengzhong reservoir dam foundation, no saturation line appeared and good seepage- prevention effect was achieved, worthy reference in similar projects.
摘要: 对升钟水库大坝基础采用低压厚幕灌浆技术方案处理后, 粘土心墙内没有形成浸润线, 灌浆帷幕防渗效果很好, 可在类似工程中推广应用。
徐俊杰. 升钟水库大坝基础灌浆防渗效果浅析[J]. .
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://magtech.dam.com.cn/EN/
http://magtech.dam.com.cn/EN/Y2007/V0/I2/51