Abstract: The damat Tuohai hydropower station has been in operation for more than 20 years, and the concrete damage by freezing – thaw at water face is serious. This paper introduced the measures in aspects such as disease elimination, safety enhancement and life prolongation of damand hydraulic structures.
摘要: 托海水电站大坝运行20 多年, 迎水面部分出现了严重冻融损坏。本文对新能托海水电站及时修补消除大坝及附属建筑物的缺陷, 提高其安全性, 延长使用寿命方面所做的工作进行了全面介绍。
伊力亚尔·加拉力丁, 马引妮. 新能托海水电站大坝、发电洞、排砂洞冻融混凝土修复处理[J]. .