Abstract: Regarding to hydropower stations on sediment-laden rivers with low regulation ability, how to control sand sedimentation is the key issue in design and operation. This paper summarized the experience of sand sedimentation control of Lubuge reservoir and analyzed its effect.
摘要: 对于位于多沙河流上调节能力差的水电工程来说,如何在工程的设计和实际运用中采取有效措施,减少有效库容淤损,是工程长期发挥效益的关键,也是水电工程设计和运用必须高度重视的问题。本文从实际运行角度总结了鲁布革水库在实际运行中控制泥沙淤积的措施,并对其实施效果进行了分析。
刘金洪. 鲁布革水库控制泥沙淤积的措施及效果分析[J]. .