Dam & Safety ›› 2022, Vol. 0 ›› Issue (2): 32-.

Previous Articles     Next Articles

Comparison and selection of design schemes for toe slab foundation of Huale reservoir dam

ZHU Shuai   

  1. Water Conservancy Investigation and Design Institute of Linfen City
  • Received:2021-11-22 Revised:2022-03-15 Online:2022-04-08 Published:2022-07-05

化乐水库大坝趾板基础设计方案比选

朱  帅   

  1. 山西省临汾市水利勘测设计院,山西  临汾,041000
  • 作者简介:朱 帅(1985— ),男,山西高平人,工程师,主要研究方向为水利工程设计。

Abstract: Based on topographic and geological conditions, two design schemes for toe slab foundation are advanced, namely foundation on bedrock or on overburden. By analysis in aspects such as project cost, construction period, implementation difficulty and et al., foundation on overburden is chosen as the final scheme.

Key words: toe slab foundation, comparison and selection of design schemes, bedrock, overburden

摘要: 基于地形条件和地质构造,拟定化乐水库大坝趾板基础设计方案一为趾板基础建在基岩上,方案二为趾板基础建在覆盖层上。从工程造价、施工工期、施工难度等方面综合分析,最终选择方案二作为化乐水库大坝趾板基础设计方案。

关键词: 趾板基础, 设计方案比选, 基岩, 覆盖层

CLC Number: