Dam & Safety ›› 2022, Vol. 0 ›› Issue (1): 32-38.
Previous Articles Next Articles
JIN Xinxin, ZHOU Shuguo, LI Libing, SHANG Yujie and ZHANG Chunyu
Received:
Revised:
Online:
Published:
金鑫鑫1,周树国2,黎利兵1,商玉洁1,张春雨1
作者简介:
基金资助:
Abstract: Based on the safety monitoring results of reconstructed Fengman dam, the deformation development law and distribution characteristics of Fengman gravity dam during the first impoundment are studied and analyzed. The results show that the horizontal deformation, settlement and inclination of the dam are all within a reasonable range. The distribution and development trend of deformation go well with general law. The deformation of transverse joint is small, and there is no anomalous development trend. The dam deformation is generally within the normal range.
Key words: reconstruction of Fengman dam, first impoundment, monitoring analysis, dam deformation
摘要: 以丰满大坝重建工程安全监测结果为基础,研究分析了丰满重力坝在首次蓄水期间的主要变形发展规律和分布特征。结果表明:大坝的水平变形、沉降变形和倾斜角度均在合理范围内,变形分布及变化趋势符合一般规律,大坝横缝变形较小,且无异常发展趋势,坝体变形总体处于正常范围。
关键词: 丰满重建工程, 首次蓄水, 监测分析, 大坝变形
CLC Number:
TV642 
 
JIN Xinxin, ZHOU Shuguo, LI Libing, SHANG Yujie and ZHANG Chunyu. Analysis and evaluation on the deformation behavior during the first impoundment period of reconstructed Fengman dam[J]. Dam & Safety, 2022, 0(1): 32-38.
金鑫鑫, 周树国, 黎利兵, 商玉洁, 张春雨. 丰满大坝重建工程首次蓄水期坝体变形性态分析评价#br#
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://magtech.dam.com.cn/EN/
http://magtech.dam.com.cn/EN/Y2022/V0/I1/32