Dam & Safety ›› 2020, Vol. 0 ›› Issue (3): 52-.

Previous Articles     Next Articles

Plant simulation test and site commissioning of spillway relay hydraulic hoist of Shuikou hydropower station

SHEN Yanping, JIN Xiaohua, SHI Shoujin, HU Mengxi, WANG Gongming and LU Bo   

  1. PowerChina Huadong Engineering Co., Ltd.
  • Received:2019-11-27 Online:2020-06-08 Published:2020-06-08

水口电站溢洪道接力式液压启闭机改造厂内试验与现场调试

沈燕萍1,金晓华1,石守津1,胡梦溪1,王功明2,陆  波2   

  1. 1. 中国电建集团华东勘测设计研究院有限公司,浙江 杭州,311122;2. 福建水口发电集团有限公司,福建 福州,350000
  • 作者简介:沈燕萍(1981— ),女,浙江嘉善人,高级工程师,主要从事水工金属结构设计。

Abstract: This paper introduces the plant simulation test and site commissioning of spillway relay hydraulic hoist of Shuikou hydropower station. As well, it summarizes the technical problems found, for reference.

Key words: relay hydraulic hoist, plant simulation test, site commissioning

摘要: 介绍了水口电站溢洪道接力式液压启闭机厂内模拟试验和现场调试试验情况,对发现的问题进行了技术总结。

关键词: 接力式液压启闭机, 厂内模拟试验, 现场调试