Abstract: As the difference of safety monitoring among concrete face slab rock-fill dam, mass concrete dam and homogeneous earth dam, some problems in the monitoring of dam settlement, horizontal displacement, seepage and face concrete stress were advanced. Further, corresponding solution were discussed, for reference.