Previous Articles     Next Articles

New method for electricity generation forecast of cascade hydropower stations on Dadu river

ZOU Zu-jian and QIU Zhi-peng   

  • Received:2013-05-11 Revised:2013-06-23 Online:2013-08-31 Published:2013-08-31

一种适用于大渡河流域梯级电站的发电量预测新方法

邹祖建,邱志鹏   

  1. 1.国电大渡河流域水电开发有限公司,四川 成都 610041;2.中国水电工程顾问集团公司,北京 100120
  • 作者简介:邹祖建(1982-),男,汉,四川绵阳人,工程师,从事水电站运行调度工作。

Abstract: By studying the characteristics of the operation of cascade hydropower stations, based on the method of water resources planning and management, the main parameters which effect the electricity generation of cascade hydropower stations are abstracted. As well, model for electricity generation forecast is established, which has better relative stability. It may reflect the utilization level of hydro energy and it's easy and simple to make the plan of electricity generation with the use of this model, worthy reference.

Key words: Dadu river, hydropower station, electricity generation, forecast

摘要: 通过研究流域梯级水电运营特点,引入水资源综合规划与管理的相关方法,提炼出梯级电站发电影响的主要参数因子,建立电站发电量预测模型,该模型具有较好的相对稳定性,可整体反映电站水能利用水平,用于电站年电量目标的制定具有计算简便、可操作性好的特点,具备一定运用价值。