ISSN 1671-1092 CN 33-1260/TK

• 贵州引子渡水电站工程建设专辑 • 上一篇    下一篇

引子渡水电站压力钢管及钢岔管设计

姚元成1,雷益川2   

  1. 1.国家电力公司贵阳勘测设计研究院.贵州贵阳 550002;2.黔源电力股份有限公司引子渡项目处,贵州贵阳 550002
  • 出版日期:2004-04-28 发布日期:2004-04-28

On penstock and bifurcated pipe designing in Yinzidu hydropower station

YAO Yuan-cheng and LEI Yi-chuan   

  • Online:2004-04-28 Published:2004-04-28

摘要: 根据引子渡水电站的工程规模和特点,结合主要的设计计算研究大型钢岔管的布置设计,使其结构布置安全、合理、经济,满足运行要求。

Abstract: Based on the features and project scale of Yinzidu hydropower project,large steel bifurcated pipe layout,which made it safe,rational and economic was studied in combination with primary design calculation.Therefore it could meet the operation re-quirement.?