ISSN 1671-1092 CN 33-1260/TK

大坝与安全 ›› 2017 ›› Issue (3): 58-.

• 补强加固 • 上一篇    下一篇

滩坑水电站导流洞堵头渗漏处理

刘远财   

  1. 浙江浙能北海水力发电有限公司,浙江 杭州,310009
  • 收稿日期:2017-03-06 修回日期:2017-03-13 出版日期:2017-06-08 发布日期:2017-06-08
  • 作者简介:刘远财(1983- ),男,浙江丽水人,工程师,主要从事水电站运行管理工作。

Leakage treatment of diversion tunnel plug in Tankeng hydropower station

LIU Yuan- cai   

  1. Zhejiang Zheneng Beihai Hydropower Co., Ltd.
  • Received:2017-03-06 Revised:2017-03-13 Online:2017-06-08 Published:2017-06-08

摘要: 针对滩坑水电站导流洞堵头渗漏问题,详细分析了渗漏原因,并介绍了渗漏处理方案及施工技术要求,对堵头渗漏处理效果做出评价。

关键词: 滩坑水电站, 导流洞, 渗漏, 处理

Abstract: In this paper, the reasons for leakage of diversion tunnel of Tankeng hydropower station are analyzed in detail. As well, the leakage treatment scheme and technical requirements for construction are introduced.

Key words: Tankeng hydropower station, diversion tunnel, leakage, treatment