ISSN 1671-1092 CN 33-1260/TK

大坝与安全 ›› 2021 ›› Issue (3): 65-.

• 资料分析 • 上一篇    下一篇

华光潭二级水电站水库放空期间大坝观测分析

张宏燕   

  1. 浙江浙能华光潭水力发电有限公司,浙江  杭州,311322
  • 收稿日期:2020-05-09 修回日期:2020-05-15 出版日期:2021-06-08 发布日期:2021-11-25
  • 作者简介:张宏燕(1984— ),女,浙江衢州人,工程师,研究方向为水工观测。

Analysis on observation results of Huaguangtan Ⅱ hydropower dam during reservoir emptying

ZHANG Hongyan   

  1. Zhejiang Zheneng Huaguangtan Hydropower Co., Ltd.
  • Received:2020-05-09 Revised:2020-05-15 Online:2021-06-08 Published:2021-11-25

摘要: 华光潭二级水电站拦河坝由混凝土重力坝组成,对水库放空及回蓄期大坝运行监测资料进行分析,以了解大坝受水荷载的影响程度。

关键词: 华光潭二级水电站, 水库放空, 观测分析

Abstract: Huaguangtan Ⅱ hydropower dam is a concrete gravity dam. Through analyzing the monitoring data of dam operation during reservoir emptying and impounding, the influence of load on the dam can be understood.

Key words: Huaguangtan Ⅱ hydropower station, reservoir emptying, analysis of observation results

中图分类号: