千岛湖配水工程渌渚江施工导流设计与优化实施

陈永红,李向姚,朱世永   

  1. 中国电建集团华东勘测设计研究院有限公司,浙江 杭州,311122
  • 收稿日期:2018-04-04 修回日期:2018-05-02 出版日期:2018-10-08 发布日期:2018-10-08
  • 作者简介:陈永红(1970- ),男,湖南湘乡人,教授级高级工程师,从事水利水电工程施工组织设计与项目管理工作。

Design and optimization of Luzhu River diversion in Qiandao Lake water distribution project

CHEN Yong-hong, LI Xiang-yao and ZHU Shi-yong   

  1. PowerChina Huadong Engineering Co., Ltd.
  • Received:2018-04-04 Revised:2018-05-02 Online:2018-10-08 Published:2018-10-08

摘要: 杭州市第二水源千岛湖配水工程穿越渌渚江时采用了倒虹吸埋管方式,原导流规划方案涉及公路正常运营和大量淹没赔偿等。通过对导流时段的优化和选择,多方案比选了导流建筑物规模,有效控制了风险,节省了投资。

关键词: 施工导流, 导流时段, 导流建筑物, 优化设计

Abstract: Inverted siphon buried pipe is used to make across the Luzhu River in the second water source project of Qiandao Lake which is an improvement from the original diversion plan. The original diversion plan would affect the normal operation of highway and would include large amount of compensation for the submergence. By schemes comparison and optimization, the appropriate scale of diversion structure is selected, in which the risk is well controlled and investment is saved.

Key words: construction diversion, diversion period, diversion building, optimal design