大坝与安全 ›› 2013 ›› Issue (5): 32-35.

• 资料分析 • 上一篇    下一篇

黄河龙羊峡水电站大坝接缝开合度监测资料分析

王雪梅,孔庆梅   

  1. 青海黄河上游水电开发有限责任公司大坝管理中心,青海 西宁,810016
  • 收稿日期:2013-08-25 出版日期:2013-10-31 发布日期:2013-10-31
  • 作者简介:王雪梅(1967-),女,河北省青县人,高级工程师,从事水电站大坝安全管理工作。

Analysis of the joint opening of Longyangxia reservoir dam

WANG Xue-mei and KONG Qing-mei   

  1. Dam Management Center of Upstream of Yellow River Hydropower Development Co., Ltd.
  • Received:2013-08-25 Online:2013-10-31 Published:2013-10-31

摘要: 龙羊峡水电站大坝坝高、库大、地质条件复杂,且大坝长期在低水头下运行,大坝的运行性态是大家十分关注的问题。从测缝计长期监测资料分析,龙羊峡大坝纵横缝测缝计监测资料变化规律不同于其他同类坝型测缝计资料的变化规律,且通过对测缝计监测资料变化规律的分析可以看出坝体接缝的状况。

关键词: 龙羊峡水电站大坝, 施工缝, 测缝计, 监测资料, 变化规律

Abstract: Because of complex geological condition, large dam height and storage as well as high operation water level, the operation performance of Longyangxia reservoir dam attracts lots of attention. By analysis on monitoring data by joint meters, the different changing law of the joint opening could be summarized and the joint condition could be assessed.

Key words: Longyangxia reservoir dam, construction joint, joint meter, monitoring data, law of opening